| Price List of Ground Floor Raheja Highway Arcade |
| Floor |
Area (Sq.ft.) |
Rate |
| Ground Floor |
435.72 |
Rs. 7200/- per sq. ft. |
| First Floor |
306.550 |
Rs. 6700/- Rs per sq. ft. |
| Second Floor |
461.844 |
Rs. 6200/- per sq. ft. |
| Third Floor |
912.323 |
Rs. 5700/- per sq. ft. |
| PLC Applicable on Ground Floor |
| Highway |
15% |
| Corner |
10 |
| Atrium |
10% |
| Drive Way |
10% (Applicable only on Ground Floor) |
| Down Payment Plan |
| Stages |
Payment |
| On Application for booking |
10% of BSP |
| Within 60 days of booking |
85% of BSP +100% of PLC + 100% of parking+100% cost of optional features, if any+100% EDC & IDC
|
| On receipt of occupation certificate* |
5% of BSP + IFMS+ Registration Charges |
| Installment Payment Plan |
| Months |
Tentative Construction Schedule* |
Installment to be paid |
| At the time of Booking |
|
10 % of BSP |
| Within 60 days of Booking |
|
15% of BSP |
On date of offer of
Allotment (deemed allotment) |
|
5% of BSP +50% EDC & IDC+25% of PLC+
25% of Parking slot. |
| Within 2 months of deemed allotment |
On start of Excavation work/ Construction work |
5% of BSP +50% EDC & IDC+25% of PLC +25% of Parking slot. |
| Within 5 months “ “ “ |
On start of Foundation laying |
5% of BSP + 50% of PLC + 50% of Parking slot |
| Within 8 months “ “ “ |
On start of Basement roof slab |
10% of BSP+100% cost of optional features |
| Within 11 months “ “ “ |
On start of Ground floor roof slab |
10% of BSP |
| Within 14 months “ “ “ |
On start of 1st floor roof slab |
10% of BSP |
| Within 17 months “ “ “ |
On start of 2nd floor roof slab |
5% of BSP |
| Within 20 months “ “ “ |
On start of 3rd floor roof slab |
5% of BSP |
| Within 24 months “ “ “ |
On start of 4th floor roof slab |
5% of BSP |
| Within 28 months “ “ “ |
On start of Finishing |
5% of BSP |
| Within 32 months “ “ “ |
On application of occupancy certificate |
5% of BSP |
| Within 36 months “ “ “ |
On receipt of occupancy certificate |
5% of BSP+ IBMS + Registration Charges |
* Which ever is earlier. #Extra service taxes are payable as per the prevailing rates.
Note:-
1. The construction schedules shown are indicative and approximate & does not affect the due date of payment of installment. In the event if construction is pre-poned the installment become due accordingly. In case the construction gets delayed beyond 60 days due to any reason whatsoever, the Company may suspend collection of installment till it falls due, at its sole discretion.
2. In case the purchaser makes any prepayment for any of the installment as stated above, the Developer has a right to retain/refund the excess money received from the purchaser. If the Developer decides to keep such amount, an interest of 9% p.a. calculated on monthly basis for the period of prepayment of installments will be paid to the Purchaser by the Developer on the amount of prepayment provided such amounts have been lying with the company for more than six months.
3. In case of Increase/Decrease of the number of floors time linked payment schedule shall follow proportionately divided into no. of floors.
4. If the booking is made in between /after the first launch date, the entire amount of installment(s) payable till that date shall have to be paid within 60 days of the booking along with any other installment which falls due during the period of such 60 days, otherwise penal interest will be charged as per the terms and conditions. |
| Enquiry For Residential Apartment Raheja Highway Arcade |
| Project Enquiry Form |
Resale Project Posting Form |
|
|
|
|
|
 |
Raheja Developers has initiated a remarkable plan of Highway Arcade that is perfectly relatable and relevant to the needs and demands of the commoners. The upsurge in residential and Industrial Development has led to a high demand for a Local Shopping Center in the area. Surrounded by residential gated communities like Aashiana, Bestech, Konark, Omaxe, M2K, Parsvnath and upcoming Raheja Iconic Tower on the highways etc. and located adjacent to the NH-8. Raheja Highway Arcade is the first organized shopping complex in the area and thus has a ready consumer base - from everyday highway commuters to daily convenience shoppers. |
| We are online real estate company, property dealers, property consultant in Daruhera. Our property advisors are always available to assist you with all the details about the project (Specifications, Floor plans, Price, Payment Schedule, etc.) and help you Identify an apartment of your choice. |
| This is planned through single - point provision of host of facilities and services which include courtyard style mixed usage development, open air convenience retail including restaurants, cafés, entertainment thrills, banquet hall, large food courts, Banks, ATMs and Financial Institutions coupled with efficient and cost effective quality office spaces. |
|
| USPs of Highway Arcade Dharuhera: |
1. Dharuhera is easily accessible from Delhi NCR.
2. Prominent neighboring areas like Gurgaon, Bhiwadi, Rewari & Manesar.
3. Gateway of NH-8.
4. Non A/C Structure
5. Low Maintenance
6. Center of huge residential hub
7. Environmental friendly Architecture.
|
| Area start with 117 sq. ft. to 2887 Sq. ft |