Price List |
| Type |
Accomodation |
Super Area |
Basic Consideration Price |
Rs. 3145/sqft. |
| X1/X1 A |
3 BR+2T |
990 sq.ft. |
| X2 |
3 BR+2T |
951 sq.ft. |
| Y1A/Y1 |
2 BR+2T |
766 sq.ft. |
| Z1 |
1 BR+1T |
460 sq.ft. |
|
Preferential Location Charges (PLC)
|
Ground Floor |
Rs.75/ sq.ft |
1st Floor |
Rs.50/ sq.ft |
2nd Floor |
Rs.40/ sq.ft |
Landscape Facing |
Rs.50/ sq.ft |
|
Other Charges |
| Covered Car Parking |
Rs.150000/- each |
Surface Car Parking |
Rs.75000/- each |
Apart from the basic consideration price & PLC following amounts are payable by the Allottee at per sq.ft of the super area of the apartment |
|
Lease Rent |
Rs.95/- |
IFMSD |
Rs.50/- |
Electric sub-station charges |
Rs.40/- |
| |
| # In addition, Electric Connection charges and Charges on account of External Electrification Work as demanded by Competent Authority, are payable extra. |
| * Car parking allotment will be done on first come first serve basis at the time of possession . |
| • Common Maintenance Charges for a period of 2 years (Two years) to be determined at the time of offer of possession on the basis of super area of apartment + Service taxes and any other levies as applicable from time to time shall be payable extra. |
| • Company would pay charges @ Rs. 5/- per sq.ft. of the super area per month for any delay attributable to the inability of the Company subject to Force Majeure, on the handing over of the Apartment beyond the committed period of 24 months from the date of signing of Terms & Conditions of Allotment till the date of issue of notice of possession . |
| • Similarly, the allottee(s) would also be liable to pay holding charges @ Rs. 5/- per sq.ft. of super area per month if the allottee(s) fails to take possession within 42 days form the date of issuance of the notice of possession. |
Note :- The above Prices/Payment Plans are subject to revision/withdrawal at any time without notice and at the sole discretion of the Company.
Registration charges, as applicable for required documents shall be payable extra by the allottee(s).
|
Payment Plans |
Down Payment Plan - 'A' Rebate @ 8% on BCP |
| At the time of Registration |
10% of BCP |
| Within 45 Days of Registration / Allotment |
85% of BCP + Lease Rent + PLC + Parking. |
| On final Notice of Possession |
5% of BCP + Sub Lease Deed Charges & other charges as applicable. |
Construction Linked Installment Plan - B |
| On Booking / Registration |
10% of BCP |
| Within 60 days of Registration / Allotment |
10% of BCP + 50% PLC |
| Within 120 days of Registration / Allotment |
10% of BCP + 50% PLC |
| On commencement of construction / development # |
10% of BCP + 50% Parking Charges |
| On completion of GF Floor Roof |
7.5 % of BCP + 50% Parking Charges |
| On completion of 2th Floor Roof |
7.5% of BCP + Lease Rent |
| On completion of 4th Floor Roof |
7.5% of BCP |
| On completion of 6th Floor Roof |
7.5% of BCP |
| On completion of 9th Floor Roof |
5% of BCP |
| On completion of Top Floor Roof |
5% of BCP |
| On completion of Masonry work within apartment |
5% of BCP |
| On Completion of Internal Plaster within apartment |
5% of BCP |
| On completion of Flooring within aprtmernt |
5% of BCP |
| On Final Notice of Possession |
5% of BCP + Sublease Dead charges & other charges as applicable |
| Note:-- |
| Other charges include Interest Free Maintenance Security Deposit, Electric Sub-Station Charges, Electric Connection Charges, Fire Fighting Charges, Centralized Communication Charges, and Common Maintenance Charges ETC. |
| This instalment and the subsequent installments (s) in the above Installment Plan shall become payable on demand irrespective of the serial order in which they are listed above. |
|