Price list |
Total Area |
: 10 Acres |
Tower |
: Tower A |
No of Floors |
: Ground + 11 |
Retail Space |
: Ground & First Floor
|
Office Space |
: 2nd to 11th Floor |
Construction Linked Payment Plan |
Basic Sales Price |
: Rs.7800/- Sq. feet super area |
Unit Size |
: 500 sq. feet super area |
Car Parking |
: Rs. 250000/- per car park |
IFMSD |
: Rs.60/- per sq. feet |
| |
At the time of booking |
15% |
Within 60 days from the date of booking |
15% |
On Start of construction work at site |
10% + 50 %cost of the car parking |
On Start of Ground Floor Roof Slab |
10% + 50% cost of the car parking |
On Start of Fourth Floor Roof Slab |
10% |
On Completion of RCC Super Structure |
10% |
On Completion of Brick Work |
On Completion of Brick Work 15%
|
On Completion of Flooring & Plaster |
On Completion of Flooring & Plaster
10% |
At the time of possession |
5%+Stamp Duty & Registration Charges+IFMSD |
|
|
Down Payment Plan |
At the time of booking |
15% |
Within 60 days from the date of booking |
80% + car parking |
On Possession |
5%+Stamp Duty + Registration Charges + IFMSD |
|
|
|
At the time of booking |
Rs. 5 Lakhs (Simplex 240 Sq. yds )
Rs. 7.5 Lakhs (Simplex 360 Sq. yds )
Rs. 10 Lakhs (Duplex 240 Sq. yds )
Rs. 15 Lakhs (Duplex 360 Sq. yds) |
With in 30 days of booking |
10% of ( BSP +PLC) less amount paid on booking |
Within three months or Allotment, whichever is later |
10% of ( BSP +PLC) |
On Start of Development work at the site |
10%of (BSP +PLC) |
Completion of Foundation DPC of the Unit |
10% of ( BSP +PLC) |
Casting of First Floor Roof |
10% of (BSP +PLC) |
Completion of the brick work of the unit |
10% of (BSP +PLC) |
Completion of the Plaster work of the unit |
10 of ( BSP +PLC) |
On the Completion of the Flooring of the unit |
10% of ( BSP +PLC) |
On the Completion of the painting work of the unit |
10% of (BSP +PLC) |
On Possession |
10%of (BSP +PLC) +IBMS +Cost of stamp Duty & other charges |
Down Payment Plan (10% rebate) |
| At the time of booking |
Rs. 5 Lakhs (Simplex 240 Sq. yds )
Rs. 7.5 Lakhs (Simplex 360 Sq. yds )
Rs. 10 Lakhs (Duplex 240 Sq. yds )
Rs. 15 Lakhs (Duplex 360 Sq. yds |
With in 30 days of booking |
10% of (BSP +PLC) less amount paid on booking |
Within Three months or Allotment, whichever
is later |
80% of ( BSP +PLC) |
On Possession |
10%of (BSP +PLC) + IBMS + Cost of Stamp Duty and Registration charges |